Phase 1 of the Gateway 85 project includes the construction of two (2) tilt panel shell warehouse buildings totaling 909,127 sf on approximately 85-acres. The project includes full site development with public infrastructure to the site. The buildings consist of one building at 286,727 sf with a rear load 32’ clear height and 35 docks. The second building is a 622,400 sf cross-dock with a 40’ clear height and 62 docks. The entire project including sitework is on schedule to be completed start to finish within 12 months.
Charlotte, NC
North Point Development
studioNorth Architecture
In-Progress